BP plug Gulf of Mexico well

BP have confirmed that the MC252 well has been capped 

BP have confirmed that the MC252 well has been capped since July 15; there is currently no oil flowing into the Gulf. BP continues to work with the guidance and approval of the National Incident Commander and the leadership and direction of the federal government.

Following the completion of cementing operations on the MC252 well on August 5rh, pressure testing was performed which indicated there is an effective cement plug in the casing. BP believes the static kill and cementing procedures have been successful.

BP continues to progress the relief well operations that commenced on May 2. The well is currently at a measured depth of 17,909 feet. Progressing towards the intersect with the MC252 well will involve drilling alternating with ranging runs to confirm proximity to the well. Depending upon weather conditions it is expected that the first relief well will intercept the MC252 well annulus in mid August.

Operations on the second relief well, which started May 16, have been suspended at a measured depth of 15,874 feet, so as not to interfere with the completion of the first relief well.

On the surface work continues to identify and collect oil to clean up oil that has reached shore. Since July 15, no new oil has flowed into the Gulf of Mexico from the MC252 well. As a result, BP, as part of Unified Command, has conducted overflights and other reconnaissance and has found less skimmable quantities of oil over the last several days. To date, skimming operations have recovered a total of over 826,000 barrels of oily liquid and a total of 411 controlled burns have been carried out.