Government consultations on compensating those affected by the proposed HS2 high-speed rail scheme have been ruled

Government consultations on compensating those affected by the proposed HS2 high-speed rail scheme have been ruled

The government's HS2 high-speed rail scheme suffered a setback when the High Court ruled that the consultation process for compensating those affected by the multibillion-pound project "was so unfair as to be unlawful".

The decision was a victory for the High Speed 2 Action Alliance (HS2AA), consisting of more than 70 affiliated action groups and residents' associations.

The HS2AA case on consultation was one of five separate cases brought to block the controversial scheme in its current form. It was the only case to succeed.

Mr Justice Ouseley, sitting at London's High Court, is now hearing submissions from lawyers on the appropriate remedy.

The first phase of HS2 would see a high-speed line running through Tory heartlands from London to Birmingham.

A second phase extends the line to Leeds and Manchester to create what will become known as "the Y network".

The project is designed to cut journey times, ease overcrowding and boost regional business.

The government hailed the court's decision on the cases it won as a "landmark victory" and said the loss on the compensation case would "not affect the HS2 construction timetable in any way".

Rail Minister Simon Burns said: "This is a major landmark victory for HS2 and the future of Britain.

The judge has categorically given the green light for the government to press ahead without delay in building a high-speed railway from London to Birmingham, Manchester and Leeds."

The then transport secretary Justine Greening gave HS2 the go-ahead in January 2012.

The judge said the £33 million scheme might in future be extended to Glasgow and Edinburgh, while the first phase would include a direct link with the existing high-speed Channel Tunnel rail link (HS1).

The judge stressed that it was not his task to review the merits of HS2 itself, but to consider whether the decisions setting it up were legally flawed.

He identified 10 grounds raised in the five cases brought by various opponents, including 18 local councils, scores of residents' associations and action groups, plus farmers and a golf club.

He rejected nine out of 10 of the grounds, which included attacks on the manner in which the project had been steered through Parliament and alleged breaches of EU environmental and habitat directives.

He also dismissed allegations that the government failed to take account of relevant issues and was guilty of indirect discrimination because of the impact of redevelopment of London's Euston station on the local ethnic minority community.

The 10th - and only successful - challenge was HS2AA's claim that the consultation and decision-making process on compensation was "fundamentally unfair".

Some 172,000 properties within 0.6 miles (1km) of the first phase are alleged to be affected by "HS2 blight".

David Wolfe QC, appearing for HS2AA, said tens of thousands of people who "just happen to live and own properties" along the high-speed route faced loss of value on their homes and being unable to move or remortgage for 15 years or more.

Mr Wolfe told the judge that 172,000 affected households had been contacted. 

Householders faced inadequate compensation and the prospect of unfairly being made to suffer because of the claimed public interest in HS2 going ahead.

He said the consultation process was flawed because of "lack of detail" and insufficient information from Ms Greening on the options for a discretionary compensation scheme.

Allowing the HS2AA challenge, Mr Justice Ouseley ruled: "Although the overall decision is not irrational, the carefully reasoned and substantial HS2AA consultation response addressing the consultation issues as framed by the Secretary of State cannot have been conscientiously considered.

"All in all, the consultation on compensation was so unfair as to be unlawful."

Latest Issue

E&T cover image 1607

"As the dust settles after the referendum result, we consider what happens next. We also look forward to an international summer of sport."

E&T jobs

  • Digital Forensic Specialist (Audio)

    Met Police
    • London
    • Circa £37,305 plus £3,406 location allowance

    You’ll contribute to a wide range of research and development activities.

    • Recruiter: Met Police

    Apply for this job

  • MetOp-SG Receiver Project Manager

    Science and Technology Facilities Council (STFC)
    • STFC Rutherford Appleton Laboratory, Harwell, Oxfordshire
    • £37,213 - £50,926 (depending on experience)

    Project Manager to oversee the development, production and test of spaceflight components and integrated receiver systems

    • Recruiter: Science and Technology Facilities Council (STFC)

    Apply for this job

  • Systems Engineer

    Reaction Engines Ltd
    • Abingdon, Oxfordshire
    • Competitive + Benefits

    Perform general systems engineering tasks as necessary with specific focus on electronic systems and instrumentation.

    • Recruiter: Reaction Engines Ltd

    Apply for this job

  • Production Manager

    Reaction Engines Ltd
    • Abingdon, Oxfordshire
    • Competitive + Benefits

    An amazing opportunity to plan, direct and coordinate all manufacturing operations and activities in line with company strategy and business plan.

    • Recruiter: Reaction Engines Ltd

    Apply for this job

  • Navigation Sensors Principle Engineer

    MBDA
    • Stevenage
    • Competitive Salary & Benefits

    What?s the opportunity? An exciting opportunity has arisen in a rapidly evolving international team with increasing capabilities.  The Navigation Sensors Group is responsible for the...

    • Recruiter: MBDA

    Apply for this job

  • Technology Manager - External Communications

    BAE Systems
    • Frimley, England, Surrey
    • Negotiable

    Technology Manager - External Communications Would you like Lead the technical delivery of the External Communications System (ECS) capability sustainment & evolution projects within the common ECS (cECS) Baseline Design Management (BDM) programme? Th

    • Recruiter: BAE Systems

    Apply for this job

  • Graduate Process Engineer

    EFFECT Photonics
    • Brixham, Devon
    • £20,000 to £25,000

    Join our exciting journey to deliver new standards in the availability of data bandwidth.

    • Recruiter: EFFECT Photonics

    Apply for this job

  • Senior Principal Materials Engineer

    MBDA
    • Stevenage
    • Competitive salary & benefits

    What?s the opportunity? A fantastic opportunity has arisen for an experienced materials engineer/scientist specialising in non-metallic materials and processing. You will be given responsibility for...

    • Recruiter: MBDA

    Apply for this job

  • Postdoctoral Research Associate

    The University of Liverpool
    • Liverpool, Merseyside
    • £32,600 - £37,768 pa

    Applications are invited for a Postdoctoral Research Associate in a brand new area of communications.

    • Recruiter: The University of Liverpool

    Apply for this job

  • Test Engineering Opportunities

    HMGCC
    • Hanslope Park, Milton Keynes
    • Salary offered will depend on skills and experience

    Push incredible innovations beyond their limits. Opportunities for Software, Hardware, EMC, Test and Inspection Engineers!

    • Recruiter: HMGCC

    Apply for this job

More jobs ▶

Subscribe

Choose the way you would like to access the latest news and developments in your field.

Subscribe to E&T